SRT Board Approves 655-Day Extension for Thai-Chinese Railway Contract 3-3, Citing Delayed Site Handover; Ayutthaya Station Requires New One-Year Design Study
The SRT Board has approved a 655-day extension for the Thai-Chinese Railway Contract 3-3, covering the Ban Dai Ma–Lam Takhong section, until 19 June 2...